WHAT IS GEOTECHNICAL INSTRUMENTATION AND MONITORING?

What Is Geotechnical Instrumentation and Monitoring?
When you excavate a deep basement in a city centre or construct a tunnel close to existing buildings, the surrounding ground can move. Even small movements can affect nearby structures, roads, railway lines and underground utilities.
You cannot simply assume that everything will behave as expected. You need to measure what is happening while construction is underway.
This is where geotechnical instrumentation and monitoring (GIM) comes in.
It is part of my day-to-day work at Sixense UK. My work involves infrastructure monitoring systems, instrumentation, telemetry and the management of the data collected from construction sites.
In simple terms, geotechnical monitoring helps engineers understand how the ground and surrounding structures behave during construction. It provides measurements that can be compared against design predictions and agreed project limits.
What Does Geotechnical Monitoring Actually Mean?
Geotechnical monitoring involves installing instruments in the ground, on retaining walls and on nearby structures to measure movement, pressure, loads and other physical changes.
Depending on the project, monitoring might include:
- Ground movement around an excavation
- Settlement of nearby buildings and roads
- Changes in groundwater pressure
- Movement of retaining walls
- Loads acting on temporary structural supports
- Movement and deformation of railway tracks
The instruments collect measurements at agreed intervals. These readings are then made available to engineers and construction teams through monitoring systems and software.
The important thing is not just collecting measurements. It is understanding what those measurements mean.
For example, if a retaining wall starts moving more than expected, engineers need to know whether this is within the predicted behaviour or whether something needs investigating.
Monitoring provides that information while construction is progressing, rather than waiting until visible damage appears.
The Sensors We Install in the Ground
Some of the most important monitoring instruments are installed below ground. Once construction progresses, these instruments may be difficult or impossible to access, so their installation and commissioning need careful planning.
Here are some commonly used instruments:
Inclinometers
Inclinometers measure lateral ground movement.
They are commonly installed in vertical boreholes using special grooved casing. Survey measurements taken inside the casing help establish how the ground is moving at different depths.
For automated monitoring, in-place inclinometer systems can be installed to collect readings without requiring someone to visit the instrument for every survey.
They are particularly useful around deep excavations, retaining walls and potentially unstable slopes.
Extensometers
Extensometers measure displacement between reference points or anchors installed at different positions.
For example, a multi-point extensometer installed below an excavation can help engineers understand how different ground layers are moving.
They can be used to monitor settlement, heave and other ground displacement, depending on their installation and orientation.
Piezometers
Piezometers measure pore water pressure within the ground.
Vibrating wire piezometers are commonly used in construction monitoring. Changes in pore water pressure can have a significant effect on soil behaviour and ground stability.
They are particularly important when working below the groundwater table or carrying out excavations where groundwater conditions need to be controlled.
Earth Pressure Cells, Strain Gauges and Load Cells
These instruments help engineers understand the forces acting on structures and temporary supports.
Earth pressure cells measure pressure acting on a surface, while strain gauges measure deformation in structural elements. Load cells measure forces acting on elements such as anchors, tiebacks and temporary steel props.
Together, these measurements help engineers compare actual structural behaviour against design expectations.

Monitoring Buildings, Roads and Railway Lines
Ground movement does not stop below the surface. It can affect nearby buildings, roads, bridges, utilities and railway infrastructure. For this reason, monitoring often extends beyond the excavation itself.
Automated Robotic Total Stations (ARTS)
Automated total stations are widely used to monitor the movement of surrounding structures.
The instruments are installed at carefully selected locations, ideally with a stable reference network, and automatically measure optical prisms fixed to buildings, retaining walls and other structures.
Using electronic distance and angular measurements, the system calculates the three-dimensional coordinates (X, Y and Z) of each prism. By comparing these coordinates over time, engineers can identify movement and settlement.

Depending on the monitoring arrangement, readings can be collected throughout the day and night without requiring a surveyor to visit every monitoring point.
However, automated survey systems still need regular maintenance, instrument checks and suitable environmental corrections. A clear line of sight and reliable reference points are also essential.
Railway Track Monitoring
Railway infrastructure requires particular attention when construction takes place nearby.
Monitoring can include track geometry surveys, precision track trolleys, automated survey measurements and wireless tilt sensors.
Measurements typically include:
- Track settlement
- Track cant and cross-level
- Track twist
- Changes in alignment
- Localised movement
The permitted movement limits depend on the railway infrastructure, the monitoring specification and the applicable railway requirements.
Even relatively small movements can be important, which is why monitoring data needs to be reviewed against project-specific limits.
The Real Challenge: Data and Telemetry
Installing instruments is one thing. Getting reliable readings from them throughout a construction project is another challenge altogether.
A large infrastructure project can have hundreds of monitoring instruments distributed across a wide area. Many of these instruments are connected to automated data loggers that collect readings at scheduled intervals.
The loggers then transmit the information to central monitoring systems, often using mobile networks or other wireless communication technologies.
Depending on the instrument and location, systems may use batteries, solar panels or external power supplies. This is where things can become difficult:
Communication problems
Underground structures, deep excavations and enclosed spaces can make wireless communication difficult. Mobile network coverage is not always reliable, particularly when instruments are installed below ground or behind concrete structures.
Power management
Remote loggers need a reliable power supply. Battery capacity, solar charging, transmission frequency and environmental conditions all affect how long a system can operate without maintenance.
Construction site conditions
Construction sites are not friendly environments for electronic equipment. Dust, cement, water, vibration and accidental damage from machinery can affect instruments, cables, loggers and solar panels.
A logger that was working perfectly yesterday might stop transmitting after nearby construction activities.
Missing or unreliable readings
A communication failure does not necessarily mean that an instrument has stopped measuring. Sometimes the logger continues collecting data but cannot transmit it.
In other cases, the instrument itself may have developed a problem. Understanding the difference is important when investigating missing readings or unexpected changes.
This is why monitoring does not finish when the instruments are installed. The telemetry network needs regular checks, maintenance and attention throughout the construction period.
Turning Raw Readings into Useful Information
Collecting measurements is only part of the job. Engineers need to understand what the readings mean.
Monitoring data can be affected by several factors, including temperature, environmental conditions, instrument behaviour and construction activities.
For example, steel structural elements can expand when temperatures rise and contract when temperatures fall. This can create regular changes in strain or load measurements throughout the day.
If these effects are not understood, engineers might interpret normal environmental changes as actual structural movement. This is where data validation and engineering interpretation become important.
At Sixense, automated and manual monitoring readings can be brought together through our Beyond Monitoring platform. The platform provides a central place to review monitoring information, examine trends and compare measurements against agreed project limits.

Projects commonly use a traffic-light system to communicate monitoring status:
- Green: Readings are within normal operating limits.
- Amber: An agreed warning threshold has been reached and requires investigation or engineering review.
- Red: An agreed action threshold has been reached and requires an immediate response from the project team.
The exact response depends on the project, its monitoring requirements and the procedures agreed by the organisations involved.
Automated alerts can also be configured to notify the relevant people by email or SMS when readings cross specified thresholds.
The important point is that an alert is not a replacement for engineering judgement. Someone still needs to understand the reading, check the circumstances and decide what action is appropriate.
Field Lessons: Why Reliable Data Matters
Working with instrumentation and monitoring systems has taught me that collecting data is not necessarily the difficult part. Making sure that the data is reliable and available when people need it is often the bigger challenge.
Consider a simple example: an automated total station reports that a building prism has moved by several millimetres. Before drawing any conclusions, someone needs to consider whether the prism has been disturbed, whether the instrument reference points are stable, whether environmental conditions have affected the measurements and whether the change is consistent with other monitoring points.
The same applies to underground instruments and telemetry systems. A missing reading, an unusual measurement or a sudden change in a data trend needs investigation.
On a major infrastructure project, monitoring information is used by different teams to make decisions. Engineers, surveyors, construction managers and monitoring specialists all need access to information they can trust.
That is why I see geotechnical monitoring as more than installing sensors and collecting numbers. It is about connecting instruments, communication networks, software and engineering knowledge to provide a reliable picture of what is happening on site. And that is what makes the data side of this industry just as important as the instruments themselves.
Technical Standards and Further Reading
For anyone interested in learning more about geotechnical instrumentation and monitoring, these are useful starting points: - BS EN ISO 18674: Geotechnical investigation and testing – Geotechnical monitoring by field instrumentation. This is a series of standards covering general monitoring principles and different types of instrumentation. - CIRIA C760: Guidance on embedded retaining wall design. Includes guidance on retaining wall design, construction, monitoring and the Observational Method. - British Geotechnical Association (BGA): A useful source of geotechnical engineering publications, technical guidance and industry information.
Geotechnical monitoring brings together civil engineering, instrumentation, surveying, telecommunications and data management. It is an important part of making sure that construction work behaves as expected and that surrounding infrastructure remains safe throughout the process.